Break the job into what it consumes
Start from the drawing, brief or scope, not from an old price. List each material with its quantity and the wastage you actually see on the shop floor. Then list each stage of work and the skill it needs.
Ask the person who will do the work to estimate the hours. Compare that with the last two similar jobs if you kept the records. An estimate from the shop floor beats one from the sales desk.
- Materials, with quantity, today's supplier rate and a wastage allowance
- Labour hours for each stage, by skill level
- Machine hours wherever a machine is the bottleneck
- Outside work such as plating, printing, transport or installation
- One-off costs: tooling, samples, travel and site visits
Build an hourly rate that carries the costs nobody bills
An hour of work costs more than the wage. Rent, power, supervision, idle time and the accounts and dispatch staff are all paid from the hours you sell.
Take last year's overheads and divide them by the hours actually sold to customers, not the hours people were present. Your accountant can pull the overhead figure from the books. Use the same rate on every quote until you review it.
Keep contingency and margin as separate lines
Add a contingency line for what you do not yet know: an unclear drawing, a site you have not seen, a material whose price moves weekly. Write down what it covers, so you can tell afterwards whether it was used.
Add margin last, on its own line. When margin is buried inside the cost, nobody can see how much room there is when the buyer bargains. Picture a hypothetical signage maker costing a job for a retail chain. With the margin line in plain view, the salesperson knows how far a discount can go before the job stops paying.
Print the assumptions on the quote itself
Every price rests on assumptions: quantities, finishes, the delivery point, the number of design revisions, who provides power or access on site. Put them on the quote. When the buyer changes one, you have a basis to revise the price.
A hypothetical event company quoting a school's annual day lists the number of rehearsals, the stage size and the hours of sound hire. When the school asks for an extra rehearsal, the change already has a price attached.
Ask a second person to check the sheet
A sheet checked only by the person who wrote it carries that person's blind spots. Ask the production head or someone in accounts to look for missing lines, wrong units and stale rates. These four checks take a few minutes:
- Every stage on the drawing has hours against it
- Material rates come from a supplier quote dated this month
- Transport and installation are written as included or excluded
- The margin line is visible and above the floor you set
Compare estimate with actual when the job closes
Close each job with a short comparison of estimated and actual figures for materials, hours and outside work. Note the line that moved the furthest and why.
After several jobs a pattern shows where your estimates miss. Change the sheet, not just the next price.
Job costing sheet (hypothetical fabrication job, illustrative figures)
| Line | Basis | Estimate | Note |
|---|---|---|---|
| Materials | MS sheet, 1,200 kg at ₹68 per kg, plus 5 percent wastage | ₹85,680 | Rate from a supplier quote dated this week |
| Labour | 64 hours at ₹450 per hour, overheads included | ₹28,800 | Hours estimated by the fabrication supervisor |
| Outside work | Powder coating and transport | ₹22,000 | Two quotes taken |
| Contingency | 5 percent of the three lines above | ₹6,824 | Covers one drawing revision |
| Margin | 15 percent of the four lines above | ₹21,496 | Owner's floor is 10 percent. Quote total ₹1,64,800. |
Illustrative figures only. Margin sits on its own line so whoever negotiates knows the floor.
Questions to ask before a price goes out
- To the buyer: 'What exactly is included, and what will your side provide?'
- 'How many revisions or changes does this price allow?'
- To the shop floor: 'How many hours would you need, and what slowed the last similar job?'
- 'Is this material rate from a quote this month or from memory?'
- 'If the buyer asks for a discount, which line can move and which cannot?'
Take the next enquiry and cost it on the sheet above before anyone gives a number, even if the quote goes out a day later. When the job closes, compare estimate and actual line by line. To keep that comparison running while the work is on, use You learn the margin on a job only after it closes, and by then it is too late to change it.
Is this your problem? The signs and causes are on our page Sales are up every quarter and the profit has not moved.. This guide is the method.