Count the hours each person really has

Start from a working week and subtract what is not client work. Leave, internal meetings, admin, training and sales time all come out. What remains is the honest number for each person, and it is lower than the owner expects.

Do this by name, not by team. A team total hides the fact that only one designer can do 3D work, or only one manager signs off audits.

Load signed work only, with the pipeline on its own row

Put every signed piece of work on the sheet as hours by person for each coming week. Use the phase estimates from the proposal and correct them as the job moves.

Keep likely deals on a separate row, clearly marked. Mixing them in either frightens the team with work that may never come, or hides real overload behind hopeful numbers. The pipeline row tells you when to worry; the signed rows tell you who is busy.

Let one person confirm every start date

Partners and account leads can sell. Only one person, an operations manager or a named partner, confirms a start date after looking at the sheet. Salespeople give the client a date range and say it will be confirmed.

Take a hypothetical agency signing a product catalogue for a component supplier and, in the same week, a brochure for a dental clinic. Both want the same senior designer. The person holding the sheet decides the order and tells both clients a date the team can keep.

Decide early what to do when a week goes red

Colour each person's week: green under capacity, amber close to it, red over. A red week three weeks out is a decision you can still make calmly. A red week tomorrow is a late night.

For each red week, pick one move and write who makes it.

  • Move a task to someone with spare hours and review it once
  • Agree a later date with the client whose work can wait
  • Bring in a freelancer for a defined, checkable piece
  • Pause selling the service that keeps overloading one person

Watch for the same names in red every week

If one person is red week after week, the problem is a skill held by one person, not a busy month. Train a second person on that work, even slowly, and give them a small live piece with review.

When the owner's own name is red every week, the firm is selling the owner's time. Decide which work only the owner can do, and move the rest.

Run the sheet in a short weekly meeting

Meet once a week with the people who lead client work. Look only at red and amber cells and the pipeline row. Agree moves, write them in the sheet and close.

Compare the sheet with actual timesheet hours at month end. If estimates keep falling short, fix the estimating before trusting next month's colours.

Weekly load sheet, one week (hypothetical design studio)

PersonAvailable hoursSigned work hoursPipeline hours (likely)StatusMove agreed
Senior designer303810RedClinic brochure moves to next week, client agreed
Junior designer35208GreenTakes catalogue layouts, senior reviews once
Project manager25245AmberNo new starts this week
Owner152212RedHands client calls on two jobs to project manager

Illustrative figures. Status compares signed work with available hours only; pipeline hours are shown so nobody is surprised, not counted.

Lines for selling and planning

  • Partner to a new client: 'We can start in the second half of the month. Our operations lead will confirm the exact date by Friday.'
  • Operations lead in the weekly meeting: 'Who is red three weeks from now, and what do we move today?'
  • To a client whose work can wait: 'We can give this proper attention from the 20th. Would that date work instead of the 12th?'
  • To a senior: 'Which piece of this job could the junior do if you review it once?'
  • To yourself: 'Am I red because the work needs me, or because I have not handed it over?'
Your next step

This week, list every client-facing person with their honest available hours and load only signed work against them for the next four weeks. Name the one person who confirms start dates. To make the weekly meeting short and decisive, read The Monday meeting runs long and nobody can say what was decided.

Is this your problem? The signs and causes are on our page Every decision in my business waits for me.. This guide is the method.