List every commitment, written and spoken
Start with the written ones: grant agreements, partnership letters with schools or hospitals, and outputs promised in proposals. Then add the spoken ones: what the founder told a community meeting, a district officer or a donor over tea.
Spoken promises count. A village that was told a health camp would come every quarter remembers it, whether or not a funder is paying for it.
Show which money can pay for which work
Separate restricted funds, which a funder has tied to a programme, from unrestricted funds the organisation can use as it decides. Note the period each grant covers and what it allows for salaries and office costs.
Ask your auditor how each fund must be treated before you move money between programmes. The grant agreement and the auditor decide this, not the programme team's view of what is fair.
Count people hours honestly, volunteers included
For each programme, estimate the staff hours it needs in a month: delivery, travel, reporting and supervision. Then count the hours you actually have, using leave, vacancies and travel time as they are.
Count volunteers by the hours they gave last quarter, not the hours they offered. A college group that offered every Saturday but came twice a month gives you two Saturdays.
Decide what to pause, shrink or fund
Where a programme is short of money or hours, there are three honest choices: pause it, shrink it to what you can deliver well, or find the funding before you continue. Decide with three questions in front of you.
- Who is harmed if this programme stops, and how badly?
- What does the agreement with the funder require of us?
- Does this programme still fit the purpose the organisation was set up for?
Tell funders and partners early, in writing
A funder told early about a gap has room to help. A funder who finds it in the annual report has none. Write to them with the facts, the change you propose and what will still be delivered.
Take a hypothetical learning programme working with ten government schools. With one coordinator short, it reduces to six schools for a term, writes to the corporate funder and informs the education office. Both partners know the new numbers before the next review visit, not after it.
Review the match with the board each quarter
Bring a one-page version of the commitment check to every board or trustee meeting. Show each programme, its funds, its hours and the gap, with the decision taken last quarter.
Add new commitments to the page only after the board sees what they need. A promise made at an event becomes a line on the sheet before it becomes a programme.
Programme commitment check (hypothetical non-profit, illustrative figures)
| Programme | Promised output | Funds this year | Hours needed a month | Hours available a month | Gap |
|---|---|---|---|---|---|
| After-school learning | 10 school centres | ₹18,00,000 restricted | 640 | 480 | 160 hours short |
| Women's savings groups | 25 groups | ₹6,50,000 restricted | 200 | 220 | None |
| Health camps | 12 camps | ₹2,00,000 unrestricted | 96 | 40 | 56 hours short; no funder |
| Office, accounts and reports | Monthly reports to 3 funders | ₹4,00,000 unrestricted | 160 | 120 | 40 hours short |
Illustrative figures only. Ask your auditor how restricted funds may be used before moving money between rows.
Lines for funders, partners and the board
- To a funder: 'We want to tell you early. This term we can run six centres well, not ten. Here is the plan.'
- For a partner school: 'We will be back with the full programme next term. Until then, this is what continues.'
- In the board meeting: 'Before we add this programme, which existing one gives up the hours?'
- Ask a volunteer group: 'Which Saturdays can you actually give us this quarter?'
- To the founder: 'Which promises have we made aloud that are not on this sheet?'
This week, build the commitment check for your programmes with the programme heads and the accounts person, including the spoken promises. Mark every gap and pick the one funder you need to write to first. To keep the sheet current through the year, build it into the rhythm on Planning happens in a rushed week in March, and the dates should have been in the diary a year ago.
Is this your problem? The signs and causes are on our page I find out how the month went long after it has ended.. This guide is the method.