Agree what counts as running, planned stop and idle
Write three definitions and pin them beside the machine. Running means making good parts. A planned stop is a break, a scheduled cleaning or a planned changeover. Idle is every other minute the machine is available but not producing.
Decide also how short a stop must be before it goes unrecorded. A threshold written down keeps the log honest. Without it, one operator logs every pause and another logs nothing.
Give the operator a short list of reason codes
Keep the list to eight reasons or fewer, so the operator can choose in seconds. Add an 'other' code with a note, and review those notes weekly to see if a new code is needed.
- No job planned
- Waiting for material from stores
- Waiting for setup or setter
- Waiting for first-off approval or inspection
- Breakdown or fault
- No operator available
- Power or utility failure
- Other, with a note
Read each reason as a question for a different person
A stop reason points to the person who can remove it. 'No job planned' is a question for sales and planning. 'Waiting for material' belongs to stores and purchase. 'Waiting for inspection' asks whether quality has enough people on that shift.
Repeated breakdowns on the same machine point to maintenance. 'No operator' points to the shift plan and leave cover. The log turns a vague complaint about the floor into a short list of named conversations.
Look at the pattern before you buy another machine
When orders wait, adding capacity is the obvious thought. Check the stop log first. If the machine stands idle waiting for material or approval, a second machine will wait in the same queue.
A hypothetical injection moulder supplying an appliance assembler might find that afternoon idle time comes from one inspector covering two lines. A hypothetical bakery making bread for its own counter might find the oven idle because dough preparation starts late. Neither needs new equipment first.
Review two reasons a week, with one owner each
Each week, total the idle minutes by reason. Pick the two largest and give each a named owner and a single action to try. Check the same two reasons the following week.
Keep the tone factual. If operators are blamed for what they record, the log goes quiet and the real idle time disappears from view.
Machine stop log (hypothetical rows)
| Date | Machine | Stop from | Stop to | Minutes | Reason code | Logged by | Action owner |
|---|---|---|---|---|---|---|---|
| 12 Nov | Press 2 | 10:15 | 10:50 | 35 | Waiting for material | Operator A | Stores head |
| 12 Nov | Press 2 | 14:05 | 14:30 | 25 | Waiting for first-off approval | Operator B | Quality supervisor |
| 13 Nov | Lathe 1 | 09:00 | 09:40 | 40 | No job planned | Operator C | Planner |
| 13 Nov | Lathe 1 | 16:20 | 17:05 | 45 | Breakdown, coolant pump | Operator C | Maintenance fitter |
Invented entries. Fill one row per stop above your agreed threshold, and total by reason code each Friday.
Questions to ask on the floor
- When this machine stopped today, what was it waiting for?
- Which stop reason do you see every day that nobody writes down?
- To the planner: how far ahead does this machine know its next job?
- To stores: what time does material for the first job reach the machine?
- If we removed one cause of waiting this week, which one would the operators pick first?
This week, print the reason list above, pin it beside your busiest machine and ask each shift to log every stop. On Friday, total the minutes by reason and name an owner for the top two. If rejections are also a concern, read Rejections turn up at dispatch and nobody can say which machine or shift made them next.