Define each milestone as something a visitor could check
'Thirty percent of work' cannot be checked. 'All bathroom plumbing pressure-tested and concealed' can. Write each milestone as a physical state of the site, with the test that proves it.
Agree the wording with the client before signing. A hypothetical shed for an auto parts supplier might use foundation, structure erected, roof sheeting fixed and handover. A home renovation might use demolition and plumbing, tiling and wiring, carpentry and paint, handover.
Size each payment to the cost of reaching it
List your expected cost to reach each milestone: materials, labour, subcontractors. Put the billing amounts beside them. Where cost runs ahead of billing, you are funding the client.
Early stages are heavy on material purchases, so they are where the gap opens. Move some of the billing earlier, ask for a material advance, or agree that the client buys certain items directly. The table below shows a hypothetical plan with a gap at the second milestone.
Prepare the evidence pack before you raise the bill
For each milestone, collect dated photos, a measurement or checklist sheet and the site lead's signature. Invite the client or their engineer to inspect, and record that they did or declined.
Send the pack with the invoice. A client who can see the finished work in photos has fewer reasons to wait for a site visit.
Bill on the day the milestone is reached
Make the site lead responsible for telling accounts the day a milestone is complete. Make accounts responsible for sending the bill that day or the next. Waiting for month end turns a finished milestone into a late payment.
Track the gap between completion and billing on the job sheet. If it keeps growing, the handoff between site and office is the problem, not the client.
Keep variations and retention on their own lines
Bill approved variations as separate lines with the signed note attached. Show any retention the contract allows as a deduction, with the release condition written on the invoice.
Ask your chartered accountant how tax applies to advances, milestones and retention under your contracts. Keep the answer in writing and use it on every job.
Compare billed, earned and collected each month
For each job, keep three running totals: value of work done, amount billed and amount collected. Billed far behind earned means you are slow to invoice. Collected far behind billed means the client or the evidence is the issue.
Review the three totals for every live job at the monthly close. Pick the job with the widest gap and agree one action with the site lead and accounts.
Milestone plan against cost (hypothetical ₹12 lakh home renovation)
| Milestone | Evidence | Bill amount | Cost to reach | Running billed minus cost |
|---|---|---|---|---|
| Advance at signing | Signed contract | ₹1,20,000 | ₹0 | +₹1,20,000 |
| Demolition and plumbing done | Pressure test sheet, photos | ₹3,00,000 | ₹4,50,000 | −₹30,000 |
| Tiling and wiring done | Checklist signed by site lead | ₹3,60,000 | ₹2,50,000 | +₹80,000 |
| Carpentry and paint done | Photos, client walk-through | ₹3,00,000 | ₹1,50,000 | +₹2,30,000 |
| Handover | Snag list closed | ₹1,20,000 | ₹50,000 | +₹3,00,000 |
Illustrative figures. Total billed ₹12,00,000 against cost ₹9,00,000. The second row shows the firm funding the job; a material advance there would close the gap.
Lines for the client and the team
- At signing: 'Each payment is tied to work you can see. Here is the list, with what we will show you at each stage.'
- On a material-heavy stage: 'This stage needs materials bought up front. Can we take a material advance, or would you prefer to buy the tiles directly?'
- Site lead to accounts: 'Plumbing is tested and closed today. Photos and test sheet are in the folder. Please bill.'
- To a client holding payment: 'What would you need to see to release this stage? We can walk the site with you this week.'
This week, rewrite the milestone list on one live job as checkable site states and put your cost to reach each one beside the bill amount. Find the stage where you fund the client. Whether that job still makes money is a weekly check, set out in Each site reports progress every week, but nobody can say whether the job still makes money.