Fix the same day and slot for every site
Choose one day each week when the site lead and the project manager sit with the figures. Keep it short and keep it fixed. A routine that moves each week stops happening.
Run it at the site where possible, so the pair can walk to the stack of cement bags or the half-plastered wall when a number looks odd.
Collect four counts from the site before the review
The site lead brings four numbers for the week. They come from the site, not from accounts, so they are current. Accounts reconciles them with bills at month end.
A hypothetical commercial building for a logistics firm and a villa for a family both use the same four counts. Only the activities change.
- Materials received and materials used, for the main items
- Labour days by trade, from the attendance register
- Subcontractor work measured and agreed this week
- Quantity of work completed for each main activity
Compare work done with money spent
For each main activity, estimate the share complete and multiply it by that activity's budget. That gives the value of work done. Put the cost to date beside it.
If cost to date runs ahead of the value of work done, the activity is overrunning. The table below shows a hypothetical week where brickwork has spent more than it has earned.
Look for wastage and idle labour on site
Compare materials used with the quantity of work completed. More cement used than the brickwork needs points to wastage, theft or wrong mixes. Check the store register before blaming anyone.
Count labour days spent waiting for material, drawings or another trade. Idle days cost the same as working ones. Record the reason, because the fix sits with whoever caused the wait.
Give every red line one action and one name
For each overrunning activity, agree one action before the review ends. Recount the stock, change the mix supervision, chase a delayed drawing or raise a variation for extra work the client asked for.
Write the action, the person and the date in the site sheet. Next week's review starts with last week's actions.
Send the owner one line per site
The owner does not need the full sheet from every site. Ask for one line each: value of work done, cost to date, the gap and the top action. Red sites get a call; green sites get a thank-you.
Once a month, check the weekly lines against the project cost sheet. If they disagree, find out why before trusting either.
Weekly site sheet (hypothetical villa, week 9)
| Activity | Budget | Share complete | Value of work done | Cost to date | Gap |
|---|---|---|---|---|---|
| Brickwork | ₹4,00,000 | 50 percent | ₹2,00,000 | ₹2,40,000 | −₹40,000 |
| Plastering | ₹2,00,000 | 20 percent | ₹40,000 | ₹35,000 | +₹5,000 |
| Electrical conduits | ₹1,50,000 | 60 percent | ₹90,000 | ₹90,000 | ₹0 |
| Total | ₹7,50,000 | ₹3,30,000 | ₹3,65,000 | −₹35,000 |
Illustrative figures. Value of work done = budget × share complete. A negative gap means cost is ahead of progress; brickwork needs an action this week.
Questions for the weekly site review
- To the site lead: 'Cement used is higher than the brickwork done. Where did the difference go?'
- On idle labour: 'How many labour days waited this week, and what were they waiting for?'
- On a red activity: 'What one thing do we change this week, and who checks it next Saturday?'
- Owner to project manager: 'Give me one line per site: work done, cost to date, gap and your top action.'
This week, pick one site and run the four counts and the work-done comparison for its three largest activities. Send yourself the one-line summary. For the job-level sheet that this routine feeds, read You learn the margin on a job only after it closes, and by then it is too late to change it.
Is this your problem? The signs and causes are on our page I find out how the month went long after it has ended.. This guide is the method.