List the three costs that arrive with every batch
A short run carries costs that do not change with quantity. Write them down before anyone talks about the piece rate.
The first is setup: operator and setter time, plus the machine standing still while dies, fixtures or programs are changed. The second is the material lost before the first good piece is approved. The third is the work after the run: cleaning, purging, returning tools and setting up the next job.
- Setup labour and machine time, from last good piece of the old job to first approved piece of the new one
- Trial pieces, purge material, test prints and offcuts scrapped during approval
- Changeover back, cleaning and tool wear charged to this job
Time a real changeover with a stopwatch
Planners quote a setup time from memory. Ask the supervisor to time three actual changeovers on the machine this job will use. Start the clock at the last good piece of the previous job and stop it when the first piece passes inspection.
Weigh or count what went into the scrap bin during those minutes. Note waiting time too, such as the inspector arriving late. That waiting belongs to your process, and fixing it lowers every short-run price you give.
Show setup on the quote as its own line
Two quoting methods work. You can show a setup charge as a separate line and keep the piece rate the same for every quantity. Or you can quote a price per piece for set quantity bands, with setup built in.
A hypothetical sheet-metal unit quoting a prototype lot to an equipment maker might show the setup line openly, because the buyer's purchase team compares piece rates across suppliers. A hypothetical press printing wedding cards for a family would rather quote one price per hundred cards, since a household buyer wants a single figure.
Whichever method you pick, write down the quantity at which the quote was built. A buyer who later halves the order should receive a fresh price, not the old rate.
Decide your floor before the next enquiry
Some small orders displace a long run on a busy machine. In that case the cost includes the profit you gave up on the job you moved. Ask the planner which jobs would wait if this one is accepted.
Set three rules in advance: a minimum batch per machine, a minimum order charge, and the conditions under which you decline. Write them on one page so the salesperson and the estimator answer the same way.
Compare the quote with what the job actually cost
After dispatch, record the actual setup minutes, scrap and changeover for that job beside the figures you quoted. Do this for each short run over the next month.
If the actual setup keeps running longer than quoted, either the quote figure is wrong or the changeover method needs work. Both are worth knowing before the next round of small enquiries.
Short-run quote worksheet (illustrative figures)
| Cost element | How it is counted | Run of 300 pieces | Run of 3,000 pieces |
|---|---|---|---|
| Setup | Timed changeover × setter and machine rate | ₹6,000 | ₹6,000 |
| Trial and approval scrap | Pieces scrapped × material cost | ₹1,500 | ₹1,500 |
| Running material | ₹12 per piece | ₹3,600 | ₹36,000 |
| Running machine and labour | ₹8 per piece | ₹2,400 | ₹24,000 |
| Total and cost per piece | Total ÷ pieces sold | ₹13,500, ₹45 per piece | ₹67,500, ₹22.50 per piece |
Hypothetical figures to show the method. The setup and scrap lines stay the same, so cost per piece doubles at the smaller quantity before any margin is added.
Lines for the quote conversation
- For this quantity the setup is a large part of the cost. I can show it as a separate line, or give you one price per piece with it included.
- This rate holds for the quantity on the purchase order. If the quantity changes, we will send a fresh quote the same day.
- Could you combine this with your next order, so we set up once for both?
- To the supervisor: please time the next three changeovers on this machine and note what went into the scrap bin.
- To the estimator: which job waits if we accept this one, and what does that job earn?
This week, time one real changeover on your busiest machine and write the minutes and scrap beside the setup figure your estimator uses. If they differ, update the quote sheet before the next small enquiry. For the wider question of what each order contributes, read Your biggest product by revenue can leave the least towards rent and salaries.